Date | Hours | Activity | Total Hours |
21 jan | .25 | group meeting | .25 |
23 jan | 1 | meet with a from mariah collaborative arts school to set up classroom observations | 1.25 |
28 jan | 5 | peterson garden | 6.25 |
28 jan | 2 | longhouse garden | 8.25 |
31 jan | 3.5 | first classroom observation | 11.75 |
4 feb | 2.5 | LNY set up/clean up | 14.25 |
5 feb | 4 | HEAT | 18.25 |
5 feb | 1.5 | project log | 19.75 |
24 jan | 1.5 | work on website | 21.25 |
6 feb | 3.25 | 2nd classroom observation | 24.5 |
8 feb | 1.5 | meetings after class and research for goddess circle | 26 |
9 feb | 1.25 | phone calls and emails coordinating trip to merilee's | 27.25 |
11 feb | 6.5 | Peterson garden | 33.75 |
13 feb | 3.0 | 3rd classroom observation | 36.75 |
14 feb | 3.25 | 4th classroom observation | 40 |
23 feb | .5 | phone calls coordinating carpooling to peterson garden | 40.5 |
25 feb | 6.5 | peterson garden (memorial) | 47 |
1 mar | 2 | work on website | 49 |